KPKT URGED TO EXPEDITE HANDOVER OF PPR KIBABAIG TO SABAH GOVERNMENT


Jannie inspects the Kibabaig PPR site together with Riduwan (in red shirt) and the Management Committee.

9 Mar 2021


PENAMPANG: Kapayan State Assemblyperson Jannie Lasimbang urged the federal Ministry of Housing and Local Government (KPKT) to expedite the completion of the additional work at the Kibabaig Public Housing Project (PPR) as soon as possible so that the approved applicants can immediately move in.


To Jannie's question to the state ministry through the State Assembly in Novermber 2020, she was informed that the additional work at the Kibabaig PPR to build a retaining wall was to be completed by end of September 2020.



However, due to the various problems faced including the relocation of electricity cables and disruption work due to COVID-19, it cannot be completed sooner and the remaining six blocks remain unoccupied.


“I have been receiving many appeals from the people regarding their application PPR and I am frustrated that I have to tell them that all work, including the completion of the entrance road, have to be completed before the subsequent handing over to KKTP and Penampang District Council. Some of the applicants said they have lost their jobs and could not afford to pay high rental anymore due to this COVID-19 pandemic” she said in a statement today.


During the PPR site inspection today, Penampang District Council Officer, Riduwan Darasin said that the electrical cable of the entire 8 blocks was stolen resulting in a huge loss. The inspection team also noted that the surrounding unoccupied areas are covered with uncontrolled shrubs and creepers.



"KPKT has provided funds for better security service but additional funds are also needed to allow regular maintenance of the surroundings before the place deteriorates while waiting for the other necessary work to be completed.


"The approved list of people which was completed in 2019 after undergoing a rigorous process of selection, should then be allowed to move in immediately and the management committee fees can be collected to keep the PPR running smoothly” Jannie noted.


When contacted by the Kapayan ADUN office, the contractor said that SESB is expected to complete the relocation of the underground electricity cables within one to two weeks and the extension of the retaining walls is expected to be completed by June 2021.


"I want to thank the Penampang District Council and all concerned for consistently pursuing both the Sabah and Federal Ministries to ensure PPR Kibabaig is safe for occupation and all the due diligence conducted in the process of selecting the applicants. I appeal to all applicants to bear with the delays for a bit more."


Jannie said that the number of applicants for PPR Kibabaig is far bigger that the available 8 blocks of units, and she has put forward several suggestions to the Penampang District Council including requesting the land in Kg Baru Luyang which is under the Ministry of Health.